ACTIVITY & AREA
|
WHAT TO EXPECT
|
DURATION
|
TENTATIVE DATE
|
Concrete Pours
|
- Approximately three (3) concrete pours per week
- Concrete trucks will be staged within work zones, including Eglinton Park, and will exit the west gate of either site.
- Trucks may be required to back into the site gates.
- Some pours will require temporary occupancy of the westbound curb lane, west of the Main Entrance
|
|
- Approximately three (3) pours per week
- The next pour with lane occupancy is tentatively scheduled for Saturday May 9, 2020.
|
Wall Demolition
|
- Demolition of temporary walls between Eastbourne Avenue and Lascelles Boulevard
|
- Wall demolition will take place on a 24-hours basis, with crews operating 5- days a week.
|
- Intermittent wall demolition is expected to continue through to late-May 2020.
|
Dewatering Well Maintenance
|
- Periodic maintenance of dewatering wells requires a short duration closures around wells in the roadway or sidewalk
- Use of a compressor and, occasionally, a hydro-vacuum truck is required.
|
- Maintenance will occur periodically over the course of construction
|
|
Monitoring Work
Equipment installed in various locations around the station are used to monitor ground movement during construction.
Read the construction notice for more detail.
|
- A drill is used to install monitoring equipment around the station area.
- Short duration closures are used to obtain readings from the monitors.
- If on the sidewalk, pedestrians may be rerouted around the work area
|
- Periodic installations will occur over the course of construction
- Readings will occur regularly over the course of construction
|
- Future installation dates to be confirmed
|