ACTIVITY & AREA
|
WHAT TO EXPECT
|
DURATION
|
TENTATIVE DATE
|
Concrete Pours
|
- Concrete pours will occur weekly over the next year.
- Concrete trucks will be staged in the existing laydown area on the north side of Eglinton Avenue and exit the site at the gate on the west end of the site.
- Some of the trucks will be required to back into the west gate of the secondary entrance due to coordination with other construction activities that will be underway during the concrete pour.
|
|
|
Lane Reduction for Concrete Pours
Main Entrance
|
- Periodic lane reduction west of the Main Entrance for concrete pours will occur weekly over the next six months.
- Concrete trucks will be staged in Eglinton Park and travel to the Main Entrance to facilitate the pours.
|
- Approximately 12 hours for each pour
|
- Thursday February 27, 2020 at 7 a.m.
|
Walls Demolition
|
- Inner walls demolition at the Secondary Entrance, between Oriole Parkway and Eastbourne Avenue.
|
- Wall demolitions will take place on a 24-hours basis
|
- Thursday February 20, 2020 – Tuesday February 25, 2020
- 24 hours
|
Dewatering Well Maintenance
Periodic maintenance of dewatering wells as required
|
- Periodic maintenance will be ongoing and require a short duration (1 day) enclosure around the well in the right of way.
- A compressor and occasional hydrovac truck will be used to complete the maintenance.
|
|
|
Monitoring Work
Equipment is installed in various locations around the station are to monitor ground movement during construction.
Read the construction notice for more detail.
|
- To install the monitoring equipment in the ground, crews move from location to location around the station area. Typically, a drilling machine is used to drill the hole where the monitor will be installed.
- If on the sidewalk, pedestrians may need to be routed around the work zone (sidewalks stay open). If on the roadway, a short-term lane closure may be required.
|
- Readings will be taken regularly for the duration of the project.
- Installations planned to be complete in the next few months.
|
- Ongoing monitoring.Currently installations are focused east of Secondary Entrance
|