Connection Bore Holes
West of Main Entrance and at Eglinton Park
*more details in CLC deck from September 4
|
- Additional connection holes to the tunnels are required to facilitate final lining activities and deliver concrete to the cavern level.
- Drilling of the bore holes will occur at Eglinton Park.
|
- Drilling will take approximately ten (10) days.
|
- January 14 -24, 2020
- 7am to 5pm
|
Monitoring Work
Equipment is installed in various locations around the station are to monitor ground movement during construction.
Read the construction notice for more detail.
|
- To install the monitoring equipment in the ground, crews move from location to location around the station area. Typically, a drilling machine is used to drill
the hole where the monitor will be installed.
- If on the sidewalk, pedestrians may need to be routed around the work zone (sidewalks stay open). If on the roadway, a short-term lane closure may be required.
|
- Readings will be taken regularly for the duration of the project.
- Installations planned to be
complete in the next few months.
|
Currently installations are focused east of Secondary Entrance
|