ACTIVITY & AREA
|
WHAT TO EXPECT
|
DURATION
|
TENTATIVE DATE
|
Concrete Pours
|
- Concrete pours will occur approximately once per week over the next year.
- Concrete trucks will be staged in the existing laydown area on the north side of Eglinton Avenue and exit the site
at the gate on the west end of the site.
- Some of the trucks will be required to back into the west gate of the secondary entrance due to coordination with other construction activities that will be underway during the concrete pour.
|
|
- Weekly
- December 3 and 4, 2019
|
Connection Bore Holes
West of Main Entrance
*more details in CLC deck from September 4
|
- Additional connection holes to the tunnels are required to facilitate final lining activities and deliver concrete to the cavern level.
- Drilling of the bore holes will occur just west of the Main Entrance.
|
- Drilling will take approximately one (1) week.
|
|
Ground Testing
West-side north of Burnaby Burnaby Blvd.
|
- The team will be running cables across the road and performing ground testing.
|
|
|
Dewatering Well Maintenance
Periodic maintenance of dewatering wells as required
|
- Periodic maintenance will be ongoing and require a short duration (1 day) enclosure around the well in the right of way.
- A compressor and occasional hydrovac truck will be used to complete the maintenance.
|
|
|
Monitoring Work
Equipment is installed in various locations around the station are to monitor ground movement during construction.
Read the construction notice for more detail.
|
- To install the monitoring equipment in the ground, crews move from location to location around the station area. Typically, a drilling machine is used to drill
the hole where the monitor will be installed.
- If on the sidewalk, pedestrians may need to be routed around the work zone (sidewalks stay open). If on the roadway, a short-term lane closure may be required.
|
- Readings will be taken regularly for the duration of the project.
- Installations planned to be
complete in the next few months.
|
Currently installations are focused east of Secondary entrance
|