November 22, 2019 4:59 PM | David McMahon (Administrator)

Closure of Chaplin Crescent for Overnight Concrete Pour -

November 27, 2019

On Wednesday November 27, 2019, Chaplin Crescent will be closed between Eglinton Avenue West and Russell Hill Road from 4:00 a.m. until 3:00 p.m. while crews will perform a large concrete pour.  The concrete will form part of the roof of Chaplin Station.  Only TTC buses, emergency service vehicles and local traffic will be permitted through the closure.  Sidewalk access will be maintained per the existing traffic configuration.  Once the pour is complete, the road will re-open.
 

Details

  • Wednesday November 27, 2019 beginning at 4:00 a.m. for approximately 11 hours
  • In the event of inclement weather, this activity may be rescheduled

Construction Staging

What to Expect

  • Chaplin Cres will be closed between Eglinton Ave W and Russell Hill Rd
  • Several concrete trucks will enter and exit the closure each hour
  • Overnight noise from trucks and concrete pumps can be expected
  • Site lighting can be expected
  • Property access will be maintained

Pedestrian Details

  • Pedestrian routing will remain the same

Traffic Details

  • Vehicles travelling northbound on Chaplin Cres will be required to divert at Russell Hill Rd or further south
  • Vehicles travelling southbound on Chaplin Cres will be required to turn left or right at Eglinton Ave W
  • TTC buses, emergency service vehicles, and local traffic will be permitted through the closure
  • A Paid Duty Officer (PDO) and traffic control personnel will be present during the closure